Plant Commercial Operation Date (COD)
Plant Commercial Operation Date (COD) The Plant's Commercial Operation Date (COD) was officially achieved on May 2, 2025, marking the ...
Read More
Read More
Unit Commercial Operation Date (COD) – Unit 1
Unit Commercial Operation Date (COD) - Unit 1 The Commercial Operation Date (COD) for Unit 1 was officially achieved on ...
Read More
Read More
First Synchronization Unit 2
First Synchronization Unit 2 The first synchronization of Unit 2 Steam Turbine Generator (STG) to the grid on January 28, ...
Read More
Read More
First Synchronization Unit 1
First Synchronization Unit 1 The first synchronization of Unit 1 Steam Turbine Generator (STG) to the grid was successfully carried ...
Read More
Read More
50,000,000 Safe Manhours with Zero LTI
50,000,000 Safe Manhours with ZeroLTI The achievement of 50,000,000 safe manhours with zero Lost Time Injury (LTI) was commemorated on ...
Read More
Read More
First Coal Receiving
First Coal Receiving The First Coal Receiving, which took place on May 13, 2024, marked a significant milestone in the ...
Read More
Read More
ISO 45001: 2018 Occupational Heatlh and Safety (OHS) Management System Certification
ISO 45001: 2018 Occupational Heatlh and Safety (OHS) Management System Certification PT Indo Raya Tenaga has achieved ISO 45001:2018 certification, ...
Read More
Read More
Testing Boiler #1 Initial Firing
Testing Boiler #1 Initial Firing by adding liquid ammonia. Ammonia is a primary energy source that emits zero carbon when utilised ...
Read More
Read More
Ammonia Injection for Initial Firing Boiler Unit 1
Ammonia Injection for Initial Firing Boiler Unit 1 Successful first firing of Boiler Unit 1 with ammonia injection was achieved ...
Read More
Read More
Completion of 500 kV Back Feeding Power for Plant Testing
Completion of 500 kV Back Feeding Power for Plant Testing The 500 kV back feeding power system was successfully completed ...
Read More
Read More
10,000,000 Manhours Without LTI
10,000,000 Manhours Without LTI The achievement of 10,000,000 manhours without Lost Time Injury (LTI) was commemorated on October 3, 2022, ...
Read More
Read More
Installing Boiler Unit 2 Pressure Part
Installing Boiler Unit 2 Pressure Part The Boiler Pressure Part installation for Boiler Unit 2 was carried out on July ...
Read More
Read More
Completion of the Foundation Work for Steam Turbine Generator (STG) Unit 2
Completion of the Foundation Work for Steam Turbine Generator (STG) Unit 2 The foundation work for Steam Turbine Generator (STG) ...
Read More
Read More
Completion of the Foundation Work for Steam Turbine Generator (STG) Unit 1
Completion of the Foundation Work for Steam Turbine Generator (STG) Unit 1 The completion of the Steam Turbine Generator (STG) ...
Read More
Read More
Installing Boiler Unit 1 Pressure Part
Installing Boiler Unit 1 Pressure Part The Boiler Pressure Part installation for Boiler Unit 1 on February 15, 2022. This ...
Read More
Read More
Installation of the First Steel Structure for Boiler Unit 1
Installation of the First Steel Structure for Boiler Unit 1 Completed ahead of schedule, the installation of the first steel ...
Read More
Read More
Financial Closing
Financial Closing During Covid-19 pandemic, IRT Management and all relevant Stakeholders have completed the condition precedents mostly by online meeting, ...
Read More
Read More
Signing of Engineering, Procurement, and Construction (EPC) Contract’s Limited Notice to Proceed
Signing of Engineering, Procurement, and Construction (EPC) Contract's Limited Notice to Proceed The Signing of the Limited Notice to Proceed ...
Read More
Read More
Signing of Engineering, Procurement, and Construction (EPC) Contract with Doosan-HK Consortium
Signing of Engineering, Procurement, and Construction (EPC) Contract with Doosan-HK Consortium PT Indo Raya Tenaga officially signed an Engineering, Procurement, ...
Read More
Read More
Signing of the Amended and Restated Purchase Agreement for Cooperation in the Power Provision
Signing of the Amended and Restated Purchase Agreement for Cooperation in the Power Provision On December 18, 2018, PT PLN ...
Read More
Read More
Ground Breaking Jawa 9 & 10
Ground Breaking Jawa 9 & 10 The groundbreaking of Jawa 9 & 10, 2 x 1000 MW CFSPP Project which ...
Read More
Read More


